Boulcott Hutt Stopbank consultation outline

Consultation Outline

 

 

Task

Date

Round 1: phase 1 feasibility study for stopbank alignment

Press Releases and newsletters

Meeting with affected parties

Public Meeting

April 2006 to June 2006

Round 2: phase 1 feasibility study

HRAC approval of evaluation outcomes for public consultation

Press Releases and newsletters

Meeting with affected parties

Public Meeting

HRAC endorsement of additional time for further discussions on the preferred alignment

June 2006 to November 2006

 

Round 3: phase 2 feasibility study

Letter to affected parties advising of HRAC outcome

HRAC endorsement of further investigations into Red, Green and Blue alignments

Councillor walkover

Press Releases and newsletters

Meeting with affected parties

HRAC endorsement to investigate the Boulcott Alternative

November 2006 to July 2007

 

Round 4: phase 2 feasibility study Boulcott alternative

Meeting with affected parties

Council endorsement of Boulcott Alternative

Press Releases and newsletters

September 2007 to July 2008

Mail out to key stakeholders/organisations, neighbouring residents and wider community noting start of process to gain planning approvals for the required work. 

Newsletter 6 included to provide background.

April 2009

Meetings with key stakeholders/organisations and neighbouring residents.

May – July  2009

Newsletter 7: Project Update

Attended Belmont Spring Festival

October 2009

Draft NOR and resource consent application circulated.

Executive summary sent to interested and affected parties and the wider community.

15 copies of document sent to directly affected groups or adjoining neighbours.

Additional copies sent to people who requested them

4 December 2009

Comments closed – note comments received up until late February 2010

22 December 2009

NOR and resource consent application lodged

11 March 2010

Information request from GW and HCC

23 March 2010

Further information provided

26 March 2010

Application notified

6 April 2010

Submissions closed

4 May 2010

Councillor briefing (Cr Glensor, Gr Greig, and Cr Lamason)

11 May 2010

Contacted via phone directly or left phone message approximately 60 submitters (not late submitters) to ask them whether we could meet prior to the pre-hearing meeting

May 2010

Memo sent to members of the Hutt River Advisory Committee (both Hutt and Regional councillors

17 May 2010

Draft Traffic Management Plan sent out to all affected submitters

27 May 2010

Briefing to HRAS committee members

31 May 2010

Further information request from HCC

1 June 2010

Boulcott Hutt Stopbank update from 31 May meeting to HRAS Councillors

1 June 2010

Meeting with Military Road residents

4 June 2010

Meeting with Stellin St, Charleston Ave, and Allen Street residents

8 June 2010

Meeting with Stellin St, Charleston Ave, and Taita Drive Sth residents

9 June 2010

Pre-hearing meeting held

15 June 2010

Meet with HCC

June 2010

Further Information letter sent to HCC

23 June 2010

Further information to be provided to HCC

21 July 2010

Hearing

9 August 2010